Roseberg Interceptor Rehabilitation Project

Roseberg Interceptor Rehabilitation Project

Background

This project will use a Cured In Place Process (CIPP) to line over 2500 feet of a 21” trunk line. This process will also replace approximately 20 stubs and side sewers that connect into the trunk line.

Status

This project is in design. Construction will take place in the summer of 2012.

Funding

Funding for this project is through a Public Works Trust fund Loan awarded by the State of Washington.

 